| Project | Task | Status | Timeline |
|---|---|---|---|
| Project 1: Adventure | Concept Art | Not Started | Feb 15-28 |
| Script | Not Started | Feb 20-Mar 5 | |
| Storyboarding | Not Started | Mar 1-15 | |
| Background Art | Not Started | Mar 10-25 | |
| Animation | Not Started | Mar 20-Apr 10 | |
| Voice Recording | Not Started | Mar 25-Apr 5 | |
| Sound Editing | Not Started | Apr 5-15 | |
| Video Editing | Not Started | Apr 10-20 | |
| Publishing | Not Started | Apr 20-25 | |
| Project 2: Comedy | Concept Art | Not Started | Mar 1-15 |
| Script | Not Started | Mar 5-20 | |
| Storyboarding | Not Started | Mar 15-30 | |
| Background Art | Not Started | Mar 25-Apr 10 | |
| Animation | Not Started | Apr 5-25 | |
| Voice Recording | Not Started | Apr 10-20 | |
| Sound Editing | Not Started | Apr 20-30 | |
| Video Editing | Not Started | Apr 25-May 5 | |
| Publishing | Not Started | May 5-10 |
gantt
title Animation Projects Timeline
dateFormat YYYY-MM-DD
section Project 1
Concept Art :2025-02-15, 14d
Script :2025-02-20, 14d
Storyboarding :2025-03-01, 15d
Background Art :2025-03-10, 16d
Animation :2025-03-20, 22d
Voice Recording :2025-03-25, 12d
Sound Editing :2025-04-05, 11d
Video Editing :2025-04-10, 11d
Publishing :2025-04-20, 6d
section Project 2
Concept Art :2025-03-01, 15d
Script :2025-03-05, 16d
Storyboarding :2025-03-15, 16d
Background Art :2025-03-25, 17d
Animation :2025-04-05, 21d
Voice Recording :2025-04-10, 11d
Sound Editing :2025-04-20, 11d
Video Editing :2025-04-25, 11d
Publishing :2025-05-05, 6d
Note: Projects 3-5 follow similar patterns with staggered start dates to manage resources effectively. Each subsequent project starts approximately 2-3 weeks after the previous one to prevent overload.